The Kwale Governor's residence construction project remains unfinished after five years, with officials citing delays in cost evaluation as a key obstacle to releasing funds.
Auditors revealed the project, initially awarded in the 2017-2018 financial year, has incurred Ksh105 million in costs as of June 2020. The State Department for Public Works faces criticism for not conducting a value-for-money assessment, preventing disbursement of Sh20 million in unpaid invoices.
Kwale Governor Salim Mvurya told the Senate Public Investment Committee that the National Treasury's budget controller has withheld funds until the evaluation is completed. "We requested the regional team to handle this, but the national team is occupied," he said.
The Senate capped governor's residence construction at Sh45 million in 2018 after investigations exposed inflated costs. Despite this, the Kwale project exceeds the limit, with officials warning delays will further increase expenses.
A 2020 audit found minimal progress between October 2019 and November 2020, with the contractor reportedly absent from the site. The project's completion date was extended to August 2019 but remains unmet, prompting committee members to demand faster action.