On August 10, 2019, Kenya Electricity Transmission Company (Ketraco) unveiled a Sh12.47 billion transmission line project aimed at enhancing power supply in Western Kenya. The 290km high voltage transmission line, the first 400kV utility line in the region, will connect the Olkaria geothermal station to the Western part of the country.

The project, which includes the construction of a 220kV transmission line between Olkaria and Lessos (213km) and from Lessos to Kisumu (77km), is expected to transmit clean, renewable energy generated from Olkaria. This will enable a stable distribution of electric power to Kenya's Western region and facilitate power interchange with Uganda.

According to Ketraco Managing Director Fernandes Barasa, the project will increase power supply reliability and capacity to meet the region's energy demands. The region, known for its sugarcane farming, fishing industries, and jua kali sector, will benefit from the stable electricity supply. Kisumu International Airport is also set to benefit from the project, which will enable it to maintain its operations.

Next read

Sports Fund CEO Nuh Ibrahim Exposed Over Refusal to Repay Ksh 2 Million Debt as Protest Looms at Talanta Plaza

24 July 2026 · 4 min read

Sports Fund CEO Nuh Ibrahim has been exposed over his refusal to repay a KSh2 million debt to a young businessman, with a peaceful...